Construction Updates

Fire-EMS Fire House No. 1 
August 2018 Update:

  • The building roof decking started the week of July 30th.
  • Exterior masonry is ongoing with the bays on the North and South sides 90% completed. 
  • Interior framing of walls is now 80% complete. 
  • The above ceiling mechanical, electrical and plumbing was completed the week of August 6th.
  • The last 30 feet of the driveway from the bays to Davis is scheduled to be poured in September along with the center median cut and the installation of the warning pedestal on the North and South side of Davis.  This will be a three-phase approach to have minimal impact on lane closings. (See map below.) Town staff will start communicating regarding temporary traffic changes to all our stakeholders over the next few weeks and electronic information boards will be on Davis Blvd two weeks before the construction starts.

Fire Station/EMS - North Side of Bay Area

Fire Station - August 2018

Fire Station/EMS - Four Bay Area

Fire Station/EMS - August 2018