Click to Home

Go To Search

HomeRSSPrintEmailFacebookTwitter

General

Posted on: July 5, 2017

Dove Road Reconstruction Update


The Town of Westlake staff’s original plan was to have Dove Road closed in 2 phases: 1) FM 1938 to Randol Mill and; 2) from Randol Mill to Sam School Road.  However, the reconstruction project is now running 3 weeks behind schedule due to rain and franchise utilities being in the way.  The gas line was finally relocated last week.  During excavation of the existing box culverts, the contractor damaged two phone cable that was not previously located.  We later learned they were abandoned AT&T cables.    

We will be changing the construction schedule to ensure we are finished before school starts in August.  The section of Dove Road between FM 1938 and Randol Mill will remain closed while we start the section of Dove Road east of Randol Mill.

Stabilization of Dove Road west of Randol Mill is complete and we have installed the first course of base asphalt binder. The plan is to cover the roadway with at least 1-1/2 inches of asphalt binder before this weekend to help with dust control over the holidays.  

After June 30
th, we will not have a paving crew on the job site until next Thursday to finish up any remaining work on the west side; the contractor working on the box culvert and the Town’s contractor working on miscellaneous items will be on site.  

We are planning to place the final asphalt surface after the box culvert work being performed by the Quail Hollow developer is complete (approximately 4 weeks).
 

Two additional message boards have been ordered and set up alerting motorists of the construction that the east leg, including Southlake’s portion of the project Randol Mill) will be under construction next week.  For this work, we will set up flaggers to flag traffic through the active construction area (one way at a time) while we work on the east leg. 

We will complete the east leg the last week of July, including the final surface layer of asphalt, and complete the section on the west side of Randol Mill where the box culvert is being installed.    

Facebook Twitter Google Plus Email

Other News in General

Dove Road is Now Open!

Posted on: August 17, 2017

Westlake to Attract Emerging Artists

Posted on: August 7, 2017

Westlake Wins

Posted on: August 1, 2017

Westlake Makes Prestigious List

Posted on: July 18, 2017

Westlake's Town Hall is on the Move

Posted on: July 12, 2017

Westlake Dream Home

Posted on: July 1, 2017

Westlake's Decoration Day Events

Posted on: May 25, 2017

Business is Booming Along Highway 114

Posted on: March 17, 2017
police badge

Prayer vigil tonight at Keller PD

Posted on: July 8, 2016

Street Maintenance Update

Posted on: July 6, 2016
water

What's on tap?

Posted on: June 16, 2016
Mayor Wheat taking oath of office

May 2016 Election Canvassed

Posted on: May 17, 2016
prayer_thumb.jpg

National Day of Prayer Event

Posted on: May 12, 2016
Christopher McGuire

An Evening in Seville

Posted on: May 12, 2016