Each week until completion, Town staff will provide you with updates on the Dove Road reconstruction project. Here is the very latest information from our crews on the scene.
- New paving is complete over the entire project.
- The opening date goal is to have the road opened Aug. 21st.
- Stone work veneer on the bridge/culvert will take two more weeks to complete, but will not stop the opening of the road.
- Total rainfall for August is 2.27 inches.
Each week until completion
If you have any questions about the Dove Road reconstruction, please email the Town of Westlake’s Project Manager, Pat Cooke at pcooke@westlake-tx.org, or call 817-727-5053.
Again, we sincerely thank you for your patience.