Our department is a digital-only, paperless department. All construction plan applications must be submitted by email to Nick Ford upon completion of a pre-application meeting.
After approval from the Planning and Zoning Commission and the Town Council, the Public Works Department of the Town of Westlake is responsible for the review and release of development projects. The Public Works Department reviews roadways, grading, drainage, water, sewer, and other utilities to ensure compliance with town ordinances, engineering standards, construction details, state and federal laws, and best engineering practices.
View the Construction Plan Development Process (PDF)
Construction plans and specifications must be prepared under the direct supervision of a licensed Professional Engineer registered in the State of Texas, and must be sealed by the Engineer of Record. A completed Construction Plan Application and Construction Plan Checklist is required with the initial submittal of civil construction plans for review, and must be attached to the plan set. In addition, application fees are assessed at the time of submittal in accordance with Ordinance 864. Subsequent submittals may have additional plan review fees.
Application and revisions will only be accepted through a pre-scheduled appointment with a pertinent Town development review staff member. The purpose of the appointment requirement is to ensure all required items are included and/or addressed prior to acceptance by the Town.
The developer must submit a digital set(.pdf) of the construction plans to Town Staff via email after the pre-application appointment.
New public infrastructure improvements associated with residential, commercial, and industrial development are reviewed by the town’s Development Review team. Construction plans must be submitted at the Town Hall upon completion of a pre-application meeting. Plans are typically reviewed within 10-20 business days depending on the size and scope of the development.
Prior to any construction taking place on the project site, a Pre-construction Conference must take place. Attendees should include the Developer, the Engineer of Record, the General Contractor, and all sub-contractors that will be constructing public infrastructure. All contractors must register with the Town of Westlake before construction is to commence.
Prior to scheduling a pre-construction meeting, the Public Works department must have the following:
All of the following are required for final acceptance of the project: